Certified payroll for a week with no work performed

Federal rules only require a certified payroll for weeks when covered work happens. But payrolls must be numbered in sequence, and many agencies and prime contractors want a "no work performed" payroll for every gap week so they can see none is missing. The generator below makes one in a minute: tick "no work", fill the header, download.

What the rules say

When to send one

SituationNo-work payroll?
Agency or prime asks for weekly payrolls including gapsYes, every week from your first week on site until your final payroll
Payrolls numbered in sequence, agency doesn't ask for gap weeksUsually not required federally; the sequence shows nothing is missing
Work stopped for weeks or months (weather, design change)Send written notice that work is suspended, or keep sending no-work payrolls
Before your first day on siteNo. Payrolls start with the first week you work on the project
After your final payrollNo. Mark the last week worked as final and stop
California public works with no work that weekStatement of Non-Performance if your contract or awarding body expects weekly records

How to fill a no-work WH-347

  1. Header: project name and number, your business name and address, prime or subcontractor, wage determination number and the week ending date.
  2. Payroll number: the next number after your last payroll. If your last was No. 6, this is No. 7.
  3. Page 1 body: no workers. Write "NO WORK PERFORMED DURING THIS WEEK" across the worker area. The generator prints this for you.
  4. Page 2: the certifying official signs and dates it as usual. With nobody paid, the apprentice and fringe tables stay blank or "N/A".
  5. Final payroll box: leave it unticked, unless your last working week has already passed and the agency wants a closing payroll.

Numbering, worked through

A subcontractor works weeks 1–3, has two weeks off while another trade finishes, and works weeks 6–7.

Week endingOn site?Payroll No. (gaps reported)Payroll No. (gaps skipped)
Mar 7Yes11
Mar 14Yes22
Mar 21Yes33
Mar 28No4 (no work)—
Apr 4No5 (no work)—
Apr 11Yes64
Apr 18Yes7, final5, final

Either way, a reviewer can see there's no missing payroll. Don't mix the two methods on one project.

California: Statement of Non-Performance

In DIR's eCPR XML, a no-work week is a payroll with statementOfNP set to true and no employee records; DIR's XML guidelines say employee information "is not added" in that case. DIR's FAQ also lets you file a Statement of Non-Performance to replace a payroll that was submitted in error for a week with no work. Each contractor and subcontractor submits its own records directly to the Labor Commissioner, at least monthly. Tick "no work" in the generator and the eCPR XML comes out as a Statement of Non-Performance (Pro).

Common mistakes

Sources

This page explains common practice as of November 2026 and is not legal advice. Your contract and the agency's instructions govern.

Questions

Do I need a payroll for a week with no work?

Not under the federal rule itself, if your numbering is sequential or you've given written notice of suspension. Many contracts and primes require one anyway.

Does a no-work week get a payroll number?

Yes, if you submit one: the next number in sequence.

Do I sign a no-work payroll?

Yes. It's a certified payroll like any other.

What about a week with only a few hours?

That's a regular payroll with those workers and hours, not a no-work payroll.